Combining Monte Carlo Simulation and Bayesian Networks Methods for Assessing Completion Time of Projects under Risk

Bibliographic Data

ID15500082
AuthorsAli Namazian (0000-0001-5957-0620, University of Tehran, corresponding author), Siamak Haji Yakhchali (University of Tehran), Vahidreza Yousefi (University of Tehran), Jolanta Tamošaitienė (0000-0003-4692-6821, Vilnius Gediminas Technical University)
Year2019
Volume16
Issue24
Pages5024-5024
Publication date2019-12-10
Open AccessYes
TypeARTICLE
VenueInternational Journal of Environmental Research and Public Health (JOURNAL)
Journal identifiersISSN: 1661-7827 • E-ISSN: 1660-4601
PublisherMultidisciplinary Digital Publishing Institute (PUBLISHER • CH)
DOI10.3390/ijerph16245024
PMID31835528
OpenAlexW2995489488
LanguageEN
Citations received3
References cited29

In this study, Monte Carlo simulation and Bayesian network methods are combined to present a structure for assessing the aggregated impact of risks on the completion time of a construction project. Construction projects often encounter different risks which affect and prevent their desired completion at the predicted time and budget. The probability of construction project success is increased in the case of controlling influential risks. On the other hand, interactions among risks lead to the increase of aggregated impact of risks. This fact requires paying attention to assessment and management of project aggregated risk before and during the implementation phase. The developed structure of this article considers the interactions among risks to provide an indicator for estimating the effects of risks, so that the shortage of extant models including the lack of attention to estimate the aggregated impact caused by risks and the intensifying impacts can be evaluated. Moreover, the introduced structure is implemented in an industrial case study in order to validate the model, cover the functional aspect of the problem, and explain the procedure of structure implementation in detail

Bayesian network · Business · Extant taxon · Machine learning · Monte Carlo method · Risk analysis (engineering · Risk assessment · Risk management · Statistics · Computer Science · Construction Project Management and Performance · Mathematics · Occupational Health and Safety Research · Risk and Safety Analysis

  • Smart City Dimensions and Associated Risks

    Open Access•Reem Al Sharif, Shaligram Pokharel•Sustainable Cities and Society•2022

  • Risk management in smart cities

    Adalberto Freitas, Carlos Rafael Silva de Oliveira et al.•Environmental Hazards•2025

  • Mapping risk scenarios of environmental impact assessment accidents in construction projects

    Open Access•Ting Yuan, Bo Shu et al.•Environmental Impact Assessment…•2023

Citations per year0.75
Citation span2022 - 2025 (4)
Highly citedNo

Tools

Open DOISci-HubOpen Access
Ethnos_APP • Open Source Project • MIT License • Frontend v2.0.0 • Privacy and Cookies • API Documentation: api.ethnos.app/docs • API Source Code: GitHub • DOI: 10.5281/zenodo.17049435 • Frontend Source Code: GitHub • DOI: 10.5281/zenodo.17050053 • cruz.rio.br • Expectantes Misericordiae